Before a single wall goes up, a new single-family home on a finished lot in St. George, Utah owes about $33,496 in impact fees: $17,266 to the Washington County Water Conservancy District and $16,230 to the City of St. George, per the district's 2026 fee schedule and the city's posted impact fee schedule as of November 23, 2026. Next door in Washington City the same math comes to $35,522. Those numbers come before the lot, the building permit, the utility hookups and the house itself, and they are the part of a build budget that is easiest to leave out. This post walks through what it actually costs to build a house in Washington County, Utah, fee by fee, with the source and date for every figure, and it tells you plainly where the published numbers stop.

Cost to build a house in St. George, Utah: impact fees, permits and lot prices in 2026

How much does it cost to build a house in St. George, Utah?

The honest answer has two halves, and only one of them is published. The fixed half is the government side: impact fees, the building permit, plan review and utility connections, which together pass $36,000 on a full-size home on a finished St. George lot once you add the connection charges, the permit and plan check to the $33,496 in impact fees. Those come from adopted schedules, so you can calculate them to the dollar. The variable half is the lot and the construction itself, and no government agency or trade group publishes a construction cost per square foot for Washington County. Anyone quoting you one precise local number is quoting a builder's bid, a national estimating database, or a guess.

So below you get the fixed half to the dollar, lot prices from this site's November count, and why the square foot number has to come from a bid. That beats a range wide enough to be meaningless.

The water district impact fee: $17,266, and it applies everywhere in the county

The single biggest fee on a new house here is not a city fee at all. The Washington County Water Conservancy District charges a regional water impact fee of $17,266 for a standard residential connection on a three-quarter or five-eighths inch meter, which the district calls a Water Efficient Connection. That figure is on the district's impact fees page and on its March 2026 single-family impact fee flyer, both read November 23, 2026, and it comes from the Impact Fee Facilities Plan and Analysis the district board adopted on December 1, 2025. The district applies it on top of whatever your city charges, so it hits a build in St. George, Washington City and Hurricane alike.

The fee is large because the analysis prices the district's next ten years of water facilities per acre foot of new demand and assigns a standard home 0.59 acre feet a year, so every new house buys its share of pipelines, storage and treatment up front. When I wrote about the county's water supply in September, the district's website still showed an older $13,500 figure beside the new analysis and I could not tell you which one was in force. The district's fee page now lists $17,266, so that question is settled.

The district's flyer says the fee is due when the building permit is applied for and before it is issued, and its fee page says fees can differ with the size of the irrigated area and other factors, with specific quotes available from the district at 435-673-3617. You get an application from your city, the city completes its section, and payment goes to the district office at 533 E. Waterworks Dr. in St. George. The fee page says cash is not currently accepted and a paid fee cannot be moved to another lot. For background on why the region prices water this way, read my post on where the county's water comes from.

Where Washington County, Utah Gets Its Water, and What That Means for Building

Is there a cheaper water impact fee for a water-wise home?

Yes, if your city has adopted the district's program and you accept permanent limits on the property. A single-family home that meets the district's Ultra Water Efficiency Standards pays $11,413 instead of $17,266, a difference of $5,853, per the same March 2026 flyer and fee page. The conditions are real and they run with the land: a maximum of 2,000 square feet of drip-irrigated landscape with no lawn, no private swimming pool, a private spa no larger than 100 square feet, smart water meters, connection to public water and sewer, and a recorded plat note and water conservation easement. The district also applies its excess water use surcharge to these homes above 8,000 gallons a month.

That trade suits a low-maintenance desert yard. It is a bad fit if you or a future buyer will want a pool, because the restriction is perpetual. Ask your city whether it has adopted the program before you design around it.

City of St. George impact fees on a single-family home

The City of St. George's impact fee schedule, labeled effective April 21, 2021, is still the newest one posted on the city's impact fees page as of November 23, 2026. For a single-family home on the smallest listed water meter (0.8 inch) with a 200 amp electrical service, it charges $1,996 for culinary water, $1,516 for wastewater ($137 local plus $1,379 regional), $4,525 for parks, $2,188 for transportation, $95 for police, $320 for fire and EMS, $781 for drainage and $4,809 for power. That totals $16,230.

Two connection charges sit on the same schedule: culinary water at $223 if water is already at the lot or $1,207 if not, and a $370 power meter fee for underground service. Meter size matters: a 1 inch water meter moves the water fee from $1,996 to $4,311 and wastewater from $1,516 to $3,274, and a 400 amp panel moves power from $4,809 to $8,244. A big house with a casita and a pool can land on the larger meter.

The trap here is the date. A 2021 schedule being the newest one online does not guarantee nobody has adopted a newer one, so call the St. George Building Department at 435-627-4000 and ask for a fee estimate on your parcel before you sign a construction contract. If St. George City Power or Dixie Power serves your lot changes the power side of the budget too, and I sorted out who serves which addresses in a separate post.

Dixie Power vs St. George City Power: Who Serves Your Address and What It Costs

Impact fee (one single-family home)City of St. GeorgeWashington CitySource and date
WCWCD regional water (3/4 or 5/8 inch meter)$17,266$17,266WCWCD impact fees page and March 2026 flyer, read Nov 23, 2026
City culinary water (smallest meter)$1,996 (0.8 inch)$4,550 (5/8 x 3/4 inch)St. George schedule effective 4/21/2021; Washington City master fee schedule, read Nov 23, 2026
Sewer, local$137$1,135Same two schedules
Regional wastewater treatment$1,379$1,379Same two schedules (Washington passes through the St. George regional fee)
Parks$4,525$4,800Same two schedules
Transportation or streets$2,188$2,941Same two schedules
Police, fire and public safety$415 ($95 police, $320 fire)$416Same two schedules
Drainage or storm water$781None per home (charged per acre at final plat)Same two schedules
Power, 200 amp single phase$4,809$3,035Same two schedules; Dixie Power sets its own fee where it serves
Total city impact fees$16,230$18,256Sum of the rows above
Total with the water district fee$33,496$35,522Sum of the rows above

Washington City impact fees, and why its total runs higher

Washington City publishes its fees in a master fee schedule, a spreadsheet linked from the city's building fee page with no effective date printed on it, which I read November 23, 2026. For one home on a 5/8 by 3/4 inch meter with a 200 amp panel it lists $4,550 for water, $1,135 for sewer, the same $1,379 St. George regional treatment fee, $4,800 for parks, $416 for public safety, $2,941 for streets and $3,035 for power. That is $18,256, about $2,000 more than St. George, mostly because Washington's water impact fee is more than double St. George's. The Washington Parkway zone adds $46 to the street fee.

Connections add $380 for water, $600 for power and $150 for the sewer inspection, another $1,130. The schedule also carries an endangered species fee of 0.2 percent of the building valuation, and it notes that power impact fees south of the Virgin River go through Dixie Power at 435-673-3297 rather than the city.

What does a building permit cost in Washington County?

A building permit on a typical home costs a few thousand dollars, far less than the impact fees, and both cities publish the formula. Washington City is the one place where every input is printed, so here is its math for a 2,000 square foot house. The city values a one and two family dwelling of standard wood frame construction at $90.35 per square foot (its Table B, labeled 2018 IBC), which puts 2,000 square feet at $180,700. The permit fee on that valuation is $1,065.36, plan review adds 45 percent ($479.41), and the endangered species fee adds 0.2 percent of valuation ($361.40), for $1,906.17 before the garage. A garage is valued separately at $31.46 per square foot.

Do not read that $90.35 as what it costs to build. It is a permit valuation table that sets the fee, not the price of the house.

St. George prints the 1997 Uniform Building Code fee scale on the same fee sheet as its impact fees. A valuation between $100,001 and $500,000 pays $993.75 for the first $100,000 plus $5.60 for each additional $1,000, so a $300,000 valuation, used here only as an example, carries a $2,113.75 permit fee. The same sheet adds plan check at 65 percent of the permit fee, a 1 percent Utah Department of Commerce fee on the building fee, and a habitat control plan fee of 0.2 percent of valuation. The city does not publish how it sets valuation on a house, so your actual number comes from the building department.

Hurricane: the fees I could not pin down

Hurricane City does not post a consolidated residential impact fee schedule that I could find and verify for this post. What the public record shows is a city in the middle of updating its fees: a power impact fee analysis amended in December 2025, a new storm drain impact fee analysis prepared in April 2026, and a secondary water impact fee update heard in December 2025. Sewer in Hurricane runs through the Ash Creek Special Service District and fire through the Hurricane Valley Fire Special Service District, each with its own fees. The water district's $17,266 applies there too, and Hurricane's secondary irrigation system is one of the factors the district looks at when it quotes a connection.

I would rather say that than guess. Building in Hurricane, La Verkin or Toquerville, get a written fee estimate on your parcel number from the city before you commit.

Hurricane Valley homes and communities

Why is there no school impact fee in Utah?

Because state law prohibits one. Utah Code 11-36a-206, titled "Prohibition of school impact fees," has barred any county, city, town, local school board or other political subdivision from imposing or collecting a school impact fee since March 21, 1995, unless the Legislature authorizes one by statute, and it has not. Section 11-36a-102 limits impact fees to water, wastewater, storm water, municipal power, roads, parks and trails, public safety, environmental mitigation and municipal natural gas facilities, which is why every fee in the table maps to one of those. It also says a building permit fee and a hookup fee are not impact fees, so those sit on separate lines of your budget.

What does a lot cost in St. George right now?

This site's own count on November 8, 2026 found 178 lots and land parcels listed inside St. George city limits at a $380,000 median asking price, and 1,275 across Washington County at a $300,000 median, where rural acreage in the outlying towns pulls the number down. Of the 178 city listings, 61 were asking $300,000 or less and 68 were at $500,000 or more. Those are asking prices that include pending deals, so treat them as the shelf, not the sale. The land page refreshes that count monthly, and my lot post covers water, septic and fault setbacks.

St. George land and lots for sale

Buying a Lot in St. George, Utah: What to Check Before You Close on Land

What about the cost per square foot to build?

No published survey gives a construction cost per square foot for St. George or Washington County. The closest first-party benchmark is the National Association of Home Builders' Cost of Constructing a Home survey for 2024, published January 2025, which found construction costs made up 64.4 percent of the average new home's sales price and the finished lot 13.7 percent. NAHB's own economist has said the survey sample is too small for any state or regional breakdown, so those are national averages. The per square foot figures you see on cost calculator websites come from national estimating databases, not from local closings, and the ones published for St. George do not agree with each other.

What I tell people who want a real number: get written bids from two licensed builders on your plans and lot, and make each one list what is excluded, such as site work, the driveway, landscaping, the fees above and utility runs from the street. Then compare bid, lot and fees against what a finished new home sells for nearby, because sometimes a spec home or a resale is the better deal. My new construction guide covers how the builder market here works.

New construction homes in St. George and Southern Utah

One cost that shows up after you move in

A home connected to the district's water system after December 31, 2022 carries a different water bill than an older house next door. Washington City's fee schedule passes through the water district's surcharge of $10 for every 1,000 gallons over a seasonal allotment for those newer connections, against $1 per 1,000 gallons over 36,000 for customers connected before that date, on top of a $1.75 monthly district charge for a 3/4 inch meter. A large lawn or a leaky drip system on a new build gets expensive in a way it does not on a 2015 house. It is one more reason the water-wise design choices above pay off twice.

Property tax on the finished home is the other ongoing cost, and it depends on the tax area and whether the home is your primary residence. My calculator covers every tax area in the county.

Southern Utah property tax calculator

Frequently Asked Questions

How much are impact fees on a new house in St. George, Utah?

About $33,496 for a typical single-family home on a finished lot, as of November 23, 2026. That is $17,266 to the Washington County Water Conservancy District plus $16,230 to the City of St. George on its schedule effective April 21, 2021, assuming the smallest water meter and a 200 amp electrical panel. Larger meters and panels cost more, so confirm your parcel with the city's building department.

Does the water district impact fee apply in Washington City and Hurricane too?

Yes. The Washington County Water Conservancy District's $17,266 regional water impact fee for a standard residential connection applies on top of city fees across its service area, including St. George, Washington City and Hurricane. Non-standard connections, such as extra meters or unusual development types, are quoted individually by the district at 435-673-3617.

Is there a cheaper water impact fee for a water-wise home?

Yes, if your city has adopted the program. A single-family home that meets the district's Ultra Water Efficiency Standards pays $11,413 instead of $17,266. The trade is permanent: no lawn, no private pool, no more than 2,000 square feet of drip-irrigated landscape, a spa no larger than 100 square feet, and a recorded plat note and water conservation easement.

Can a Utah city or school district charge a school impact fee?

No. Utah Code 11-36a-206 has prohibited any county, city, town, local school board or other political subdivision from imposing or collecting a school impact fee since March 21, 1995, unless the Legislature authorizes one by statute. A new home in Washington County pays no school impact fee.

What does it cost per square foot to build in St. George?

No published local survey answers that, and anyone giving one precise figure is quoting a bid or a national database. The National Association of Home Builders' 2024 survey found construction is 64.4 percent of the average new home's price nationally, but it is too small for a regional breakdown. Written bids from two licensed builders on your plans and lot are the only reliable number.

If you are weighing a build against buying a finished home, I can pull what comparable new and resale homes have actually sold for in the neighborhood you are considering, which is the number a build budget has to beat. Call me at 435-200-5508 or send me a message, and compare closing costs on either path with my closing cost calculator while you are at it.

Send Lance a message

St. George closing cost calculator

St. George and Washington County market report

St. George homes for sale

Sources, all read November 23, 2026:

Washington County Water Conservancy District impact fees page

WCWCD March 2026 single-family impact fee flyer

City of St. George impact fees page and fee sheet effective April 21, 2021

Washington City building fee schedule

Utah Code 11-36a-206, prohibition of school impact fees

Utah Code 11-36a-102, impact fee definitions

NAHB Cost of Constructing a Home, 2024 survey